· Permits & Florida code

No. Since 1 July 2026 Florida HOAs may no longer require an issued building permit as a condition of architectural review. You can run the HOA application and the permit application in parallel, which takes weeks out of a project.

Custom-built arched wooden gate made for a Pinellas County property
Custom-built arched wooden gate made for a Pinellas County property. Photographed on one of our own jobs.

The loop this fixes

The old sequence was maddening. The HOA would not review plans until you produced an issued permit, and you were paying for permit drawings and fees for a project the board might still reject. So most people waited, in series, and added a month to the schedule.

HB 803 addressed this directly. An association can no longer require the permit to be in hand before it will act on an architectural request.

What it does not do

Worth being precise, because this is being over-read.

  • Your HOA can still say no, on any grounds its governing documents allow.
  • Your HOA can still enforce rules on materials, colours, height, style and placement.
  • You still need the permit. This changed the order, not the requirement.
  • It does not override your declaration or your county's rules.

How to use it

  1. Submit the architectural request as soon as you have a design.
  2. Submit the permit application in parallel.
  3. Do not start work until you hold both.

Florida also tightened permit review clocks in the same bill, with short mandatory review windows for smaller single-family jobs. Between the two changes, a project that used to lose six weeks to sequential approvals can lose closer to two.

Get it in writing either way

Whatever the HOA approves, get it in writing and keep it with your permit documents. Boards change, managers change, and "the previous board said it was fine" is not a defence anyone accepts three years later when you sell.

If your association has not caught up

Many boards and management companies simply have not — the law is only a couple of months old. A polite letter citing the change is usually enough. If it is not, that is a conversation for a Florida community association attorney, not for your contractor. Saying that once and leaving it there.